Address: Noblesville, Indiana
GC/Prime/Developer:
www.cityofnoblesville.org
Sub-contractors:
Gradex Inc.
Morphey Construction, Inc.
Nes Traffic Safety
Specialties Company, LLC
Earth Images
Smock Fansler Corporation
Schutt-Lookabill Co., Inc.
Engineers:
USI Consultants www.usiconsultants.com
The new 146th street and south portion of Boden road that ties into 146th street complete a corridor from SR 37 to I-69. A new four lane highway with a median, turn lanes, median crossings, street approaches, driveways, curb and gutter, and intersection lighting. With Approximately 9 paving lane miles, there was approximately 65,196.61 sys of QA/QC 12\" Concrete pavement placed and approximataely 16,578\' of integral curb. Total project cost of $9,837,517.48