Address: 5904 S. Western Ave. Marion IN
GC/Prime/Developer:
City of Marion www.airmarion.com/Airport_Information
Sub-contractors:
Accurate Striping
McCrea Surveying
McCrite Milling
Quanta
Slusser\'s
Safety Grooving & Grinding
Specialties LLC
Engineers:
Woolpert, Inc www.woolpert.com
www.marionindiana.us
Reconstruction of runway # 15-33 for the Marion Municipal Airport. Construction broke ground on the project in October of 2007, and will be completed in the summer on 2008. This project will include pulverization of the existing runway and 20,000 cys of dirt excavation, as well as 45,464 sys of asphalt placement and lighting work.